SL NO | Name of the Project | Name of the Donor | Project Period | Type | Target | Achievement | Remarks |
1 | Rural Electrification expansion Dhaka Division Program-II | GOB | 01-07-2014 to 31-12-2019 | Equity-100% |
|
|
Completed |
2 | Up-gradation of Rural Electricity Distribution System (Dhaka, Chittagong & Sylhet Division) | GOB, IDA & BREB | 01-07-2014 to 30-06-2021 | Equity, Loan & Others | 200 KM | 199.737 KM
|
Completed
|
3 | Up-gradation, Rehabilitation and Intensification of Distribution System (Dhaka, Mymensingh, Chittagong & Sylhet Divisions)
|
GOB, ADB & BREB
|
01-07-2014 to 30-06-2021
|
Equity, Loan & Others
|
265 KM | 265 KM | Completed
|
4 | 1.5 Million Consumer Connection through Rural Electrification Expansion | GOB | 01-01-2016 to 21-12-2021 | Equity
|
1700 KM | 1710.684 KM | Completed
|
পরিকল্পনা ও বাস্তবায়নে: মন্ত্রিপরিষদ বিভাগ, এটুআই, বিসিসি, ডিওআইসিটি ও বেসিস